Renovation of Puutarhakatu

A street view from Puutarhakatu, with people crossing the street, green trees and houses on the edges.
Puutarhakatu will be renovated between the parks Vanhankirkonpuisto and Hämeenpuisto. The renovation started in March 2025 and continues until 2026. The renovation is being carried out because the water and sewer pipes have reached the end of their useful life and need to be replaced. District cooling pipes will also be built on the street.

After the renovation, the street will have a wider two-way cycle track on the northern edge, pavements on both sides and a one-way carriageway for motor vehicles. The renovation will improve walking and cycling conditions and road safety, and make the street a more pleasant environment. The management of stormwater, i.e. rainwater and meltwater, will also be improved.

Getting around and shopping on Puutarhakatu right now

The renovation of Puutarhakatu has started on 3.3.2025 from the intersections of Näsilinnankatu, Kuninkaankatu and the section between Kuninkaankatu and Aleksis Kiven katu The work will cause traffic disroptions, but the properties will be accessible by all means of transport. Through traffic on the street will be blocked during the excavation work on the carriageway. Pedestrians and cyclists will be able to travel between Aleksis Kivi Street and Hämeenpuisto.

Working hours start at 6 a.m. and end at 22 p.m. However, on Fridays, work will end at 19.30.

Traffic arragments from 31.3.

The construction of the storm and sewage drain will be moved to the south side of the Näsilinnankatu junction during the week due to future traffic changes. Minor, temporary changes to pedestrian and cycling routes will also be made as a result.  

The cable trench at Puutarhakatu 21 will be moved to Puutarhakatu 19, and from there on towards the Vapaakirkko.  Access to the properties will be secured by footbridges and driveways. Properties will be informed separately of any temporary interruptions.

At the Kuninkaankatu intersection, the renovation of the sewage and stormwater drainage system is progressing as planned. The removal of the old fire hydrant at Kuninkaankulma will result in a water cut planned for Monday 31 March from 22.00.

At the Kuninkaankatu junction, earthworks will be carried out as the renovation work progresses towards Näsilinnankatu, and the junction access routes will be opened up more widely. There may be other night-time works at Kuninkaankulma.

At the eastern end of the Puutarhakatu redevelopment, at Puutarhakatu 8, the construction of the stormwater trunk sewer is progressing towards the Kuninkaankatu junction.

Traffic arrangements on Puutarhakatu from 10.3.2025.
The work area is marked in red, the motor vehicle route in blue, the bicycle route in pink and the pedestrian route in green.

The aim is to renovate as much as possible in one go, in cooperation between the different actors, so as to cause as little inconvenience as possible and in as short a time as possible.

The renovation of the City Hall and the construction of a new building at the corner of Puutarhakatu and Aleksis Kiven katu are also underway. City Hall and its new building will be completed in spring 2026. 

Cyclists and walkers on the left, cars on the right on the street and at a stop.
View of Puutarhakatu after the renovation. (Photo: Ramboll)

Contact us

You can ask questions or give feedback about the Puutarhakatu project and the future construction site by email: puutarhakatu@tampereeninfra.fi

Your message will be forwarded to the right person.

Project actors

The City of Tampere is the main developer of the Puutarhakatu project. Tampere Water, Tampereen Energia Oy, Tampereen Energia Sähköverkko Oy and telecom operators are also involved. Tampereen Infra Oy is the main contractor of the project.  Puutarhakatu will be renewed in cooperation between the parties involved.

The renovation of Puutarhakatu will allow properties bordering the street to improve the accessibility of entrances, for example by removing low thresholds and stairs. 

Mikko Siiro
Construction of a street, commissioned by the City of Tampere: Construction engineer
Phone:
041 731 1568
Petri Kantola
Construction of a street, commissioned by the City of Tampere:
Phone:
050 364 6095
Timo Seimelä
Traffic planning, commissioned by the City of Tampere:
Pasi Palmu
Street design, commissioned by the City of Tampere:
Phone:
040 801 6812
Jukka Palonperä
Water management works, Tampere Water: Construction engineer
Phone:
050 413 1885
Karo Kilpinen
Electrical cables, district heating and district cooling, commissioned by Tampereen Energia Oy:
Phone:
040 773 9165
Juho Riikonen
Contractor, Tampereen Infra:
Phone:
041 731 0942
Aaro Liukko-Sipi
Contractor, Tampereen Infra: Foreman
Phone:
041 731 0798
Updated 28.3.2025